Türkiye lowers the home electricity limit to 3,000 kWh from 2027 and lets grid companies control larger licence-exempt plants in emergencies

From 1 January 2027, Turkish homes that use 3,000 kWh or more a year, down from 4,000 kWh in 2026, will pay the last-resort supply tariff unless they buy from a supplier, under a decision by the energy regulator, EPDK, published on 31 October 2026. About 6.5 million homes are affected; the limit for businesses stays at 15,000 kWh. Rules published on 19 October also let grid companies remotely control licence-exempt plants of 900 kW and above in emergencies, and allow batteries with no limit on storage capacity. Here is what changes, and why making your own power matters more.
What changes for homes
Each year EPDK, the Energy Market Regulatory Authority, sets the yearly consumption that makes a user a high consumer; BloombergHT calls it the subsidy limit. At or above it, a home pays the last-resort supply tariff (son kaynak tedarik tarifesi) unless it buys from a supplier under a bilateral agreement. Below it, nothing changes: EPDK said the price of the regulated national tariff (ulusal tarife) stays the same.
The limit was 5,000 kWh in 2025 and 4,000 kWh in 2026. From 1 January 2027 it is 3,000 kWh a year, about 250 kWh a month or a monthly bill of about 820 Turkish lira, according to BloombergHT. Of about 44.2 million residential subscribers, about 6.5 million, or 14.7%, will be high consumers.
| Year | Limit |
|---|---|
| 2025 | 5,000 kWh |
| 2026 | 4,000 kWh |
| 2027 | 3,000 kWh |
Not affected, according to BloombergHT: mosques and other places of worship, cemevis and associations on residential contracts, families of those killed in service, combat and disabled veterans, village drinking-water supplies, temporary shelters of AFAD, the disaster agency, and people who depend on life-support devices.
Your 2026 consumption already counts
The new limit applies from 1 January 2027, but what a home used in 2026 counts too, and the switch date depends on when it crossed the line. BloombergHT gives these examples:
- A home that first passes 3,000 kWh for the year in October 2026 moves to the high-consumer tariff on 1 January 2027.
- A home that passes it in December 2026 moves on 1 March 2027.
- A home below the limit in 2026 that passes 3,000 kWh in June 2027 moves on 1 September 2027.
What the last-resort tariff is
Under EPDK’s communiqué on the last-resort supply tariff, it is the price for users who could buy on the open market but have no bilateral agreement with a supplier. For high consumers it covers billing, retail and market energy costs plus a reasonable profit, is designed to encourage a move to the open market, and cannot be lower than the regulated single-rate tariff. In October, EPDK kept the coefficient used in the calculation at 1.05 for homes and 1.0938 for other users.
So a home above the limit has three options: stay on the last-resort tariff, buy from a supplier, or take less power from the grid.
What changes for small businesses
Not the limit. It stays at 15,000 kWh a year for industry, public and private services and lighting, and no agricultural user is affected. A business at or above 15,000 kWh without a supply agreement already pays the last-resort tariff, which reflects market energy costs. If that is your case, weigh it against supplier offers on your own consumption data.
What changes for owners of larger plants
The rules of 19 October concern licence-exempt plants (lisanssız üretim), which the regulation intends for users to meet their own needs. They deal with emergencies on the grid:
- Emergency instructions from the system operator now reach licence-exempt plants on the distribution grid. They are carried out through plants of 900 kW and above in operation, largest first.
- Distribution companies, and organised industrial zones that hold a distribution licence, may control those plants remotely. Within 15 minutes of the end of an emergency they must tell the owner by phone and in writing, and switching the plant back on is then the owner’s job.
- A plant that ignores an instruction to cut output is not paid for the output it should have cut.
- Owners in scope must ask their grid operator within 60 days of 19 October 2026, which by our count runs to 18 December, to bring their connection agreement in line with EPDK’s standard one; otherwise its terms apply. Two of its penalty clauses are suspended until 30 April 2027.
- Aggregators must set up remote control for the plants in their portfolios.
Batteries: no limit on storage capacity
Since 19 October 2026, the owner of a licence-exempt plant can add a battery up to the plant’s electrical power with no limit on its storage capacity. Power the battery sends to the grid is not paid for, so the battery is there to cover your own use, for example in the evening. Whether one pays off depends on what you use after sunset, as our battery guide explains for Spain.
Why making your own power matters more
Under the licence-exempt rules, a business can build a renewable plant tied to its own consumption without a generation licence, up to the contract power in its connection agreement, or twice that for an industrial site. Surplus fed to the grid is settled through the assigned supply company under YEKDEM, the renewable support mechanism. Every kWh the plant supplies on site is one you do not buy at the regulated or the last-resort tariff.
The new rules point to two choices: size the plant to what the site uses, because plants of 900 kW and above can be cut back in emergencies and battery exports earn nothing, and use storage to carry midday power into the evening. Our guide to commercial solar in Spain shows how a plant at your site works in practice.
How Aeternus helps
Aeternus Power is an independent energy company based in Madrid, and we are launching in Türkiye. We originate, qualify, structure and finance energy projects, solar-led and often with storage, with vetted builders and financing partners.
We never own plants: the builder or financing partner pays us a commission, never you, and only if a project goes ahead. If your business in Türkiye wants to know what a plant could cover, contact us with a year of bills: we reply within two working days. Our business page shows how we work in Spain and Portugal.
Questions
What is the electricity consumption limit in Türkiye for 2027?
From 1 January 2027, 3,000 kWh a year for homes, down from 4,000 kWh in 2026. It stays at 15,000 kWh for industry, public and private services and lighting, and agricultural users are not affected.
What is the last-resort supply tariff (son kaynak tedarik tarifesi)?
The price paid by users above the limit who do not buy from a supplier under a bilateral agreement. It covers costs, including market energy costs, plus a reasonable profit, and cannot be lower than the regulated single-rate tariff.
Does 2026 consumption count for the 2027 limit?
Yes. A home that first passed 3,000 kWh for the year in October 2026 moves to the high-consumer tariff on 1 January 2027, and one that passed it in December 2026 moves on 1 March 2027.
Who is exempt from the 3,000 kWh limit?
According to BloombergHT: places of worship and associations on residential contracts, families of those killed in service, veterans, village drinking-water supplies, AFAD temporary shelters and people who depend on life-support devices.
Can the grid switch off a licence-exempt solar plant in Türkiye?
In an emergency, yes. Instructions are carried out through licence-exempt plants of 900 kW and above, largest first, which distribution companies may control remotely, and a plant that ignores one is not paid for the output it should have cut.
Sources
- Resmî Gazete (31 October 2026, no. 33416): EPDK decision 15005 of 30 October 2026, consumption limits and coefficient for 2027 (in Turkish, PDF): https://www.resmigazete.gov.tr/eskiler/2026/10/20261031-9.pdf
- Resmî Gazete (31 October 2025, no. 33063): EPDK decision 13912 of 30 October 2025, consumption limits for 2026 (in Turkish, PDF): https://www.resmigazete.gov.tr/eskiler/2025/10/20251031-8.pdf
- Resmî Gazete (19 October 2026, no. 33405): amendment to the Unlicensed Electricity Generation Regulation (in Turkish): https://www.resmigazete.gov.tr/eskiler/2026/10/20261019-6.htm
- Resmî Gazete (19 October 2026, no. 33405): amendment to the Balancing and Settlement Regulation, Article 75 on emergency instructions (in Turkish, PDF): https://www.resmigazete.gov.tr/eskiler/2026/10/20261019-2.pdf
- Resmî Gazete (19 October 2026, no. 33405): contents of the issue, with the nine EPDK texts (in Turkish): https://www.resmigazete.gov.tr/eskiler/2026/10/20261019.htm
- Communiqué on the last-resort supply tariff, consolidated text, Articles 1 to 6 (Lexpera, in Turkish): https://www.lexpera.com.tr/mevzuat/tebligler/son-kaynak-tedarik-tarifesinin-duzenlenmesi-hakkinda-teblig/madde-6
- Unlicensed Electricity Generation Regulation, consolidated text up to 19 October 2026, Articles 1 and 5 and additional articles 3 and 4 (Alomaliye, in Turkish, PDF): https://www.alomaliye.com/wp-content/uploads/2019/05/elektrik-piy-lisanssiz-19-10-2026.pdf
- BloombergHT (30 October 2026): the subsidy limit in electricity lowered, 3,000 kWh for 2027 (in Turkish): https://www.bloomberght.com/epdk-son-kaynak-tedarik-tarifesinde-limiti-dusurdu-3792931
- Anadolu Agency via Foreks (31 October 2026): EPDK changes the consumption limit for homes (in Turkish): https://www.foreks.com/haber/detay/6ae5bdef58b1b941c2095849/AA/tr/epdk-meskenlere-yonelik-elektrik-tuketim-limitinde-degisiklige-gitti-31-10-26/
- Anadolu Agency via Foreks (19 October 2026): EPDK’s new rules for emergencies in the electricity market (in Turkish): https://www.foreks.com/haber/detay/6ad5b423422c786f3f7a529d/AA/tr/yenileme-epdk-elektrik-piyasasinda-acil-durum-uygulamalarina-yonelik-yeni-duzenlemelere-gitti-19-10-26/
- BloombergHT (19 October 2026): EPDK’s new rules on licence-exempt generation (in Turkish): https://bloomberght.com/epdkden-lisanssiz-elektrik-uretimine-iliskin-yeni-duzenleme-3791755
Latest
Europe’s power prices in early November 2026: from €184/MWh in Spain to €347/MWh in Ireland